We will be installing a 400kV overhead electricity transmission line to replace an existing 132kV overhead transmission line between Beauly and Denny.
On 6 January 2010, Ministers advised that they agreed with the Beauly-Denny public inquiry reporters' recognition of the 'pressing need' to reinforce the electricity network.
Scottish Hydro Electric Transmission owns and maintains the 132kV and 275kV electricity transmission network in the north of Scotland, in some of the UK's most challenging terrain.
On our interactive map:
Replacing the Beauly to Denny line is a complex project. To help us communicate as well as possible with people interested in its progress, and to manage the replacement work effectively, the project has been divided into four sections, one of which belongs to Scottish Power.
On 6 January 2010 Ministers stated they agreed with the Beauly-Denny public inquiry reporters' recognition of the 'pressing need' to reinforce the electricity network.